• Skip to primary navigation
  • Skip to main content
  • Skip to footer

Southern Public Power District

PO Box 1687 / 4550 West Husker Hwy
Grand Island, NE 68802-1687
308-384-2350 / 800-579-3019

  • About Us
    • Vision, Mission & Values
    • History
    • Service Area
    • Board Agendas & Minutes
    • Board Members
    • Staff
    • Careers
      • Job Openings
      • Scholarships
    • Contact Us
  • Customer Service
    • Payment & Account Portal
    • Electric Service Application
    • Rates
    • Disconnection Of Service
    • Incentive Programs
    • Distributed Generation
    • Generlink
  • News
    • Customer News Magazine
    • Annual Reports
  • Community & Development
    • Operation Round Up
    • Energy Park
    • Our Communities
  • Safety & Efficiency
    • Apogee Energy Resource Center
    • Incentive Programs
    • Hotline Trailer Demonstrations
    • Notification of Oversized Load
    • Safety Tips
      • Indoor Safety Tips
      • Outdoor Safety Tips
      • Storm Safety Tips
  • Irrigation
    • Load Control Status
    • Rates
    • Irrigation Rate Calculator
    • Construction Policy
    • Load Management Newsletter
    • Power Factor

Distributed Generation

When considering the connection of a distributed generation resource it is important to adhere to guidelines, in order to assure the safety of the general public and utility personnel, minimize potential damage to property, and prevent adverse operating conditions. We encourage potential DG operators to review the Distributed Generation Standard to identify the requirements for successful projects. Questions about these standards can be addressed to distributedgeneration@southernpd.net.

The following steps are required for customer-owned distributed generation resources to be interconnected with District facilities:

  1. Complete the District’s Application for Approval to Construct Distributed Generation Interconnection. This is required prior to constructing an interconnection to Southern Public Power District’s distribution system. It is important to complete this document early in the process so that we are aware of your intentions and can research the equipment you propose to connect. Submission instructions are included on the final page. Questions can be addressed to distributedgeneration@southernpd.net.
  2. Equipment can be purchased and construction of the interconnection can begin once the Application has been completed and accepted by both parties.
  3. Prior to closing the interconnection switch once construction is complete, an inspection by both the State of Nebraska Electrical Division (NSED) and SPPD is required. The NSED should first be contacted by your electrician.
  4. When your installation has passed NSED requirements, the customer or their electrician will be notified by NSED of their approval. The customer or electrician must then notify SPPD.
  5. A signed Agreement is the final step for interconnecting a customer-owned distributed generation resource. Upon verification of the terms of the interconnection and equipment by SPPD, both parties will sign the Agreement for the Closed Transition Operation of Distributed Generation and the interconnection switch may be closed.

Please be mindful that the installation, interconnection, and operation of a distributed generation resource without an Agreement signed by both parties shall be grounds for immediate disconnection of the District’s service without constituting a breach of contract.

Net-Metering

Pursuant to State Statue 70-2005, Southern Public Power District must publish an annual net metering report. Net metering is available to customers who install renewable fuel generators such as solar, wind, hydro or biomass sources and operate the generator in parallel with Southern Public Power District’s electrical system.

Southern Public Power District
Net Metering Report
December 31, 2022

  • 39 net metering qualified facilities.
  • The total estimated rated generating capacity of qualified facilities is 446 kW.
  • The total estimated net kilowatt-hours received from customer-generators is 345,572.
  • The total estimated amount of energy produced by customer-generators is 683,833 kWh.

Footer

Links

Nebraska Power Association
Nebraska Energy Office
Diggers Hotline
Safe Electricity

Search

Current News

  

SouthernPPD Follow

Southern Public Power District. To report an outage call 800-579-3019.

southernppd
southernppd SouthernPPD @southernppd ·
29 Mar

Be aware of electrical hazards after a flood. Downed power lines could be hidden by standing water, and the lines could still be energized: http://ow.ly/RE0p50N7Boj #SafeElectricity #FloodSafety #SPPD #PublicPower #PoweringaBrighterFuture

Reply on Twitter 1641097945738035201 Retweet on Twitter 1641097945738035201 Like on Twitter 1641097945738035201 Twitter 1641097945738035201
southernppd SouthernPPD @southernppd ·
27 Mar

Last chance to apply for a Lineworker Scholarship! Applications are being accepted through April 1. Discover more at: http://ow.ly/OwfJ50LyanL

Reply on Twitter 1640338452498591748 Retweet on Twitter 1640338452498591748 Like on Twitter 1640338452498591748 Twitter 1640338452498591748
Load More...

Copyright © 2023 Nebraska Public Power District